Panchmukhi Pearl

Project Status as on Quarter ending 30-09-2024
Updated as on 01-10-2024

Booking Status

  • Residential Apartments Booked
    30

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    18

  • Mechanical Parking Booked
    6

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK-C (G+4) 1 Under Construction
BLOCK-C (G+4) 2 Under Construction
BLOCK-C (G+4) 3 Under Construction
BLOCK-C (G+4) 4 Under Construction
BLOCK-D(G+12) 1 Under Construction
BLOCK-D(G+12) 2 Under Construction
BLOCK-D(G+12) 3 Under Construction
BLOCK-D(G+12) 4 Under Construction
BLOCK-D(G+12) 5 Under Construction
BLOCK-D(G+12) 6 Under Construction
BLOCK-D(G+12) 7 Under Construction
BLOCK-D(G+12) 8 Under Construction
BLOCK-D(G+12) 9 Under Construction
BLOCK-D(G+12) 10 Under Construction
BLOCK-D(G+12) 11 Under Construction
BLOCK-D(G+12) 12 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fitness Centre
2 Emergency Evacuation Services
3 Fire Fighting Facilty
4 Use of Renewable Energy
5 Drinking Water Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Fitness Centre
2 Under Construction Security Services
3 Under Construction Community Hall
4 Under Construction Stairs
5 Under Construction Lift
6 Under Construction Roof
7 Under Construction Lobby
8 Under Construction Septic tank
9 Under Construction Power Backup

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download