Project Status as on Quarter ending 30-06-2020
Updated as on 15-02-2021

Booking Status

  • Residential Apartments Booked
    16

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    23

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block - 1 1 Under Construction
Block - 1 2 Under Construction
Block - 1 3 Under Construction
Block - 1 4 Under Construction
Block - 1 5 Under Construction
Block - 1 6 Under Construction
Block - 1 7 Under Construction
Block - 1 8 Under Construction
Block - 1 9 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download