New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

CHARDHAM RESIDENCY

Project Status as on Quarter ending 30-09-2025
Updated as on 07-10-2025

Booking Status

  • Residential Apartments Booked
    21

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    1

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Gangotri 5 Under Construction
Badrinath 3 Under Construction
Yamnotri 5 Under Construction
Badrinath 5 Under Construction
Gangotri 5 Under Construction
Yamnotri 5 Under Construction
Badrinath 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Badrinath Internal walls
2 Gangotri Marble work
3 Yamnotri Marble work Polish
4 Yamnotri Internal Wall, Electric and Putty
5 Gangotri Internal Brick Work
6 Yamnotri Doors, Internal Wall , Plumbing
7 Gangotri Tiles

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Road
2 Under Construction Common Road

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download