Project Status as on Quarter ending 31-12-2024
Updated as on 31-01-2025

Booking Status

  • Residential Apartments Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Brick work completed. Electrical work in progress. Outside plastering work in progress. Conceal plumbing work under progress
2 Outside plastering work in progress. Conceal plumbing work under progress
3 Work done till plinth

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Brick work completed. Electrical work in progress.
2 Under Construction Brick work completed. Electrical work in progress.

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download