WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

SUNCREST ESTATE - PHASE I

Project Status as on Quarter ending 31-12-2025
Updated as on 05-01-2026

Booking Status

  • Residential Apartments Booked
    359

  • Basement Parking Booked
    122

  • Covered Car Parking Booked
    118

  • Mechanical Parking Booked
    26

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 2A 13 Completed With CC
Tower 2B 13 Under Construction
Tower 2C 13 Completed With CC
Tower 2D 13 Completed Without CC
Tower 2E 13 Completed With CC
Tower 2A 13 Completed With CC
Tower 2B 13 Under Construction
Tower 2C 13 Completed With CC
Tower 2D 13 Completed With CC
Tower 2E 13 Completed With CC
Tower 2A 13 Under Construction
Tower 2B 13 Under Construction
Tower 2C 13 Under Construction
Tower 2D 13 Under Construction
Tower 2E 13 Under Construction
Tower 2A 13 Under Construction
Tower 2B 13 Under Construction
Tower 2C 13 Under Construction
Tower 2D 13 Under Construction
Tower 2E 13 Under Construction
Tower 2A 13 Completed With CC
Tower 2B 13 Under Construction
Tower 2C 13 Completed With CC
Tower 2D 13 Under Construction
Tower 2E 13 Completed With CC
Tower 2A 13 Under Construction
Tower 2B 13 Under Construction
Tower 2C 13 Under Construction
Tower 2D 13 Under Construction
Tower 2E 13 Under Construction
Tower 2A 1 Under Construction
Tower 2E 1 Not Started
Tower 2C 1 Not Started
Tower 2D 1 Not Started
Tower 2B 1 Not Started
Tower 2A 1 Not Started
Tower 2B 1 Not Started
Tower 2C 1 Under Construction
Tower 2D 1 Under Construction
Tower 2E 1 Under Construction
Tower 2A 1 Under Construction
Tower 2B 1 Under Construction
Tower 2C 1 Under Construction
Tower 2D 1 Under Construction
Tower 2E 1 Under Construction
Tower 2A 1 Under Construction
Tower 2B 1 Under Construction
Tower 2C 1 Under Construction
Tower 2D 1 Under Construction
Tower 2E 1 Under Construction
Tower 2A 1 Under Construction
Tower 2B 2 Under Construction
Tower 2C 1 Under Construction
Tower 2D 1 Under Construction
Tower 2E 1 Under Construction
Tower 2A 1 Under Construction
Tower 2B 1 Under Construction
Tower 2C 1 Under Construction
Tower 2D 1 Under Construction
Tower 2E 1 Under Construction
Tower 2A 3 Under Construction
Tower 2B 1 Under Construction
Tower 2C 1 Under Construction
Tower 2D 1 Under Construction
Tower 2E 1 Under Construction
Tower 2A 3 Under Construction
Tower 2B 3 Under Construction
Tower 2C 7 Under Construction
Tower 2D 2 Under Construction
Tower 2E 1 Under Construction
Tower 2A 7 Under Construction
Tower 2B 6 Under Construction
Tower 2C 9 Under Construction
Tower 2D 3 Under Construction
Tower 2E 8 Under Construction
Tower 2A 10 Under Construction
Tower 2B 3 Under Construction
Tower 2C 10 Under Construction
Tower 2D 5 Under Construction
Tower 2E 10 Under Construction
Tower 2A 11 Under Construction
Tower 2B 3 Under Construction
Tower 2C 13 Under Construction
Tower 2D 9 Under Construction
Tower 2E 7 Under Construction
Tower 2A 13 Under Construction
Tower 2B 7 Under Construction
Tower 2C 13 Under Construction
Tower 2D 8 Under Construction
Tower 2E 13 Under Construction
Tower 2A 13 Under Construction
Tower 2B 8 Under Construction
Tower 2C 13 Under Construction
Tower 2D 12 Under Construction
Tower 2E 13 Under Construction
Tower 2A 13 Under Construction
Tower 2B 10 Under Construction
Tower 2C 13 Under Construction
Tower 2D 13 Under Construction
Tower 2E 13 Under Construction
Tower 2A 13 Under Construction
Tower 2B 11 Under Construction
Tower 2C 13 Under Construction
Tower 2D 13 Under Construction
Tower 2E 13 Under Construction
Tower 2A 13 Under Construction
Tower 2B 13 Under Construction
Tower 2C 13 Under Construction
Tower 2D 13 Under Construction
Tower 2E 13 Under Construction
Tower 2A 13 Under Construction
Tower 2B 13 Under Construction
Tower 2C 13 Under Construction
Tower 2D 13 Under Construction
Tower 2E 13 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Driveway
2 Driveway
3 Driveway
4 Driveway
5 Driveway
6 Driveway
7 Driveway
8 Driveway
9 Driveway
10 Driveway
11 Driveway

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Podium
2 Under Construction Podium
3 Under Construction Podium
4 Completed Without CC Front Boundary Wall
5 Completed Without CC Gate Goomty with Front Boundary Wall
6 Under Construction Basement
7 Under Construction Podium
8 Under Construction Podium
9 Under Construction Podium
10 Under Construction Podium

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download