New Please be informed that the The last date for submission of Quarterly Update of Registered Real Estate Projects is hereby extended tillĀ 28.02.2025 as per the order enclosed herewith. Click here to view the order ;  All promoters are directed to comply with the order of WBRERA vide no. 1986-RERA/L-01/2023 dated 06.12.2024 regarding Quarterly Update of Registered Projects and other instructions mentioned in the said order. Click here to view the order

IDEAL PARADISO

Project Status as on Quarter ending 31-12-2024
Updated as on 29-01-2025

Booking Status

  • Residential Apartments Booked
    63

  • Basement Parking Booked
    13

  • Covered Car Parking Booked
    57

  • Mechanical Parking Booked
    21

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Wing 1 1 Under Construction
Wing 1 1 Under Construction
Wing 2 1 Under Construction
Wing 3 1 Under Construction
Wing 1 1 Under Construction
Wing 2 1 Under Construction
Wing 3 1 Under Construction
Wing 2 1 Under Construction
Wing 2 2 Under Construction
Wing 3 1 Under Construction
Wing 2 3 Under Construction
Wing 2 4 Under Construction
Wing 3 1 Under Construction
Wing 2 5 Under Construction
Wing 2 6 Under Construction
Wing 3 2 Under Construction
Wing 3 3 Under Construction
Wing 1 1 Under Construction
Wing 2 7 Under Construction
Wing 2 8 Under Construction
Wing 3 4 Under Construction
Wing 3 5 Under Construction
Wing 1 9 Under Construction
Wing 2 10 Under Construction
Wing 3 12 Under Construction
Wing 1 10 Under Construction
Wing 2 11 Under Construction
Wing 3 12 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 UGR
2 Brick work of Wing 2
3 Flooring work & Putty work Started in Wing 2
4 Wing 1
5 Wing 2
6 Wing 3
7 Wing 1
8 Wing 2
9 Wing 3

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Boundary Wall
2 Under Construction Sales Office
3 Completed Without CC Sales Office
4 Under Construction Common Facilities
5 Under Construction Common Work

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Fire NOC 09-01-2017 30-06-2017 12-05-2017
Height clearance from Airport Authority of India (if any) 07-04-2013 31-12-2016 15-12-2016