New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     Applications are invited from the eligible and willing persons for the position of (i) Judicial Member of West Bengal Real Estate Appellate Tribunal (WBREAT) and (ii) Member of West Bengal Real Estate Regulatory Authority (WBRERA) Click here to open;    

THE PARK UNIZEN

Project Status as on Quarter ending 31-03-2026
Updated as on 06-04-2026

Booking Status

  • Commercial Unit Booked
    24

  • Basement Parking Booked
    63

  • Covered Car Parking Booked
    4

  • Mechanical Parking Booked
    6

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
TOWER: A 1 Not Started
TOWER: A 2 Not Started
TOWER: A 3 Not Started
TOWER: A 4 Not Started
TOWER: A 5 Not Started
TOWER: A 6 Not Started
TOWER: A 7 Not Started
TOWER: A 8 Not Started
TOWER: A 9 Not Started
TOWER: A 10 Not Started
TOWER: A 11 Not Started
TOWER: A 12 Not Started
TOWER: A 13 Not Started
TOWER: A 14 Not Started
TOWER: A 15 Not Started
TOWER: A 16 Not Started
TOWER: A 17 Not Started
TOWER: A 18 Not Started
TOWER: A 19 Not Started
TOWER: A 20 Not Started
TOWER: B 1 Not Started
TOWER: B 2 Not Started
TOWER: B 3 Not Started
TOWER: B 4 Not Started
TOWER: B 5 Not Started
TOWER: B 6 Not Started
TOWER: B 7 Not Started
TOWER: B 8 Not Started
TOWER: B 9 Not Started
TOWER: B 10 Not Started
TOWER: B 11 Not Started
TOWER: B 12 Not Started
TOWER: B 13 Not Started
TOWER: B 14 Not Started
TOWER: B 15 Not Started
TOWER: B 16 Not Started
TOWER: B 17 Not Started
TOWER: B 18 Not Started
TOWER: B 19 Not Started
TOWER: B 20 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Protection and Detection
2 Fire Kiosk
3 Passenger elevators
4 Grid Electricity connection
5 DG Power Back up
6 Street lighting
7 Rooftop solar system
8 Internal sewer & storm water supply & drainage system
9 Organic Waste composter
10 Sewage Treatment plant
11 Water treatment plant

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Public address & voice evacuation system
2 Not Started Landscaping
3 Not Started Swimming Pool
4 Not Started Residential Activity Centre

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 04-12-2025 10-02-2026 10-02-2026