New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

4Sight Superia

Project Status as on Quarter ending 31-12-2025
Updated as on 05-01-2026

Booking Status

  • Residential Apartments Booked
    62

  • Commercial Unit Booked
    2

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    2

  • Mechanical Parking Booked
    67

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block-Ground Floor to 1st Floor- Commercial 1 Under Construction
Block-Ground Floor to 1st Floor- Commercial 2 Not Started
Block- 3rd Floor to 17th Floor - Residencial 1 Not Started
Block- 3rd Floor to 17th Floor - Residencial 2 Not Started
Block- 3rd Floor to 17th Floor - Residencial 3 Not Started
Block- 3rd Floor to 17th Floor - Residencial 4 Not Started
Block- 3rd Floor to 17th Floor - Residencial 5 Not Started
Block- 3rd Floor to 17th Floor - Residencial 6 Not Started
Block- 3rd Floor to 17th Floor - Residencial 7 Not Started
Block- 3rd Floor to 17th Floor - Residencial 8 Not Started
Block- 3rd Floor to 17th Floor - Residencial 9 Not Started
Block- 3rd Floor to 17th Floor - Residencial 10 Not Started
Block- 3rd Floor to 17th Floor - Residencial 11 Not Started
Block- 3rd Floor to 17th Floor - Residencial 12 Not Started
Block- 3rd Floor to 17th Floor - Residencial 13 Not Started
Block- 3rd Floor to 17th Floor - Residencial 14 Not Started
Block- 3rd Floor to 17th Floor - Residencial 15 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Entrance
2 Under Construction Site Office
3 Not Started Lobby
4 Not Started Lift
5 Not Started Stair
6 Not Started Terrace

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download