1 |
Block-5, 4th floor slab casting is going on & 1st floor Brick completed |
|
2 |
Block-6, 6th floor slab casting is going on & 1st floor Brick work is in progress |
|
3 |
Block-7, 3rd floor slab casting are completed |
|
4 |
Block-8, 5th floor slab casting are completed. & 1st floor Brick work is going on |
|
5 |
Block-9, Construction is yet to start |
|
6 |
Brick work done till 2nd floor of Tower-5 |
|
7 |
Block-6, Brick work completed till 2nd floor |
|
8 |
Block-7, Brick work done till 1st floor |
|
9 |
Block-8, brick work done till 1st floor |
|
10 |
Block-9, Piling has started |
|