New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

JAGANNATH VATIKA

Project Status as on Quarter ending 31-12-2025
Updated as on 07-01-2026

Booking Status

  • Residential Apartments Booked
    14

  • Commercial Unit Booked
    4

  • Basement Parking Booked
    12

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 4 Under Construction
1 5 Under Construction
1 4 Under Construction
1 4 Under Construction
1 5 Under Construction
1 5 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Brick Work along with pluster & Wall Putty going on
2 Window & Balcony Grill Fitting, Floor Tiles Fixing, Electrical Wiring Paint & Putty
3 Window & Balcony Grill fixing, Floor Tiles Fixing, Electrical Wiring going on
4 Window & Balcony Grill fixing, Floor Tiles Fixing, Electrical Wiring Paint & Putty going on
5 Internal

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Stair, Lift, Roof Water Tank
2 Under Construction Sairs & Lift
3 Under Construction Sairs & Lift , Water Tank
4 Completed Without CC Lift, Stairs, Waer Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download