WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Laguna Bay

Project Status as on Quarter ending 30-09-2024
Updated as on 05-10-2024

Booking Status

  • Residential Apartments Booked
    174

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    137

  • Mechanical Parking Booked
    60

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 1 1 Under Construction
Tower 1 2 Not Started
Tower 1 3 Not Started
Tower 1 4 Not Started
Tower 1 5 Not Started
Tower 1 6 Not Started
Tower 1 7 Not Started
Tower 1 8 Not Started
Tower 1 9 Not Started
Tower 1 10 Not Started
Tower 1 11 Not Started
Tower 1 12 Not Started
Tower 1 13 Not Started
Tower 1 14 Not Started
Tower 1 15 Not Started
Tower 1 16 Not Started
Tower 1 17 Not Started
Tower 1 18 Not Started
Tower 2 1 Under Construction
Tower 2 2 Under Construction
Tower 2 3 Under Construction
Tower 2 4 Under Construction
Tower 2 5 Under Construction
Tower 2 6 Under Construction
Tower 2 7 Under Construction
Tower 2 8 Under Construction
Tower 2 9 Under Construction
Tower 2 10 Under Construction
Tower 2 11 Under Construction
Tower 2 12 Under Construction
Tower 2 13 Under Construction
Tower 2 14 Under Construction
Tower 2 15 Under Construction
Tower 2 16 Under Construction
Tower 2 17 Under Construction
Tower 2 18 Not Started
Tower 3 1 Under Construction
Tower 3 2 Under Construction
Tower 3 3 Under Construction
Tower 3 4 Under Construction
Tower 3 5 Under Construction
Tower 3 6 Under Construction
Tower 3 7 Under Construction
Tower 3 8 Under Construction
Tower 3 9 Under Construction
Tower 3 10 Under Construction
Tower 3 11 Under Construction
Tower 3 12 Under Construction
Tower 3 13 Under Construction
Tower 3 14 Under Construction
Tower 3 15 Not Started
Tower 3 16 Not Started
Tower 3 17 Not Started
Tower 3 18 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Facility
2 Fire Facility
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lobby
2 Under Construction Staircase
3 Not Started Lift
4 Not Started Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download