WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Uttora Chrysanthemum Residency LLP

Project Status as on Quarter ending 31-12-2020
Updated as on 12-01-2021

Booking Status

  • Residential Apartments Booked
    13

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 BUILDING CONSISTING OF 2 BLOCKS 1 Under Construction
1 BUILDING CONSISTING OF 2 BLOCKS 2 Under Construction
1 BUILDING CONSISTING OF 2 BLOCKS 3 Under Construction
1 BUILDING CONSISTING OF 2 BLOCKS 4 Under Construction
1 BUILDING CONSISTING OF 2 BLOCKS 5 Under Construction
1 BUILDING CONSISTING OF 2 BLOCKS 6 Under Construction
1 BUILDING CONSISTING OF 2 BLOCKS 7 Under Construction
1 BUILDING CONSISTING OF 2 BLOCKS 1 Under Construction
1 BUILDING CONSISTING OF 2 BLOCKS 7 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 1ST FLOOR - BRICK WORK, INTERNAL PLASTER, FLOORING, DOOR SHUTTERS, RAILING, PUTTY, ELECTRICALK WIRING COMPLETED

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction BRICK WORK, INTERNAL PLASTER COMPLETED ELECTRICAL WORK IS ONGOING
2 Under Construction Brick work, internal plaster completed, electrical work is ongoing window fixing putty railing is 60% completed

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download