WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    The last date for all the pending quarterly project updates has been extended till 30.04.2025,please upload all the pending quarterly updates within 30.04.2025 to avoid penalty.

SKYDALE

Project Status as on Quarter ending 31-03-2025
Updated as on 21-04-2025

Booking Status

  • Residential Apartments Booked
    105

  • Basement Parking Booked
    120

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
SANA 3 Under Construction
SANA 1 Under Construction
SANA 2 Under Construction
SANA 4 Under Construction
SANA 5 Under Construction
SANA 6 Under Construction
SANA 7 Under Construction
SANA 8 Under Construction
SANA 9 Under Construction
SANA 10 Under Construction
SANA 11 Not Started
SANA 12 Not Started
SANA 13 Not Started
SANA 14 Not Started
SANA 15 Not Started
SANA 16 Not Started
SANA 17 Not Started
SANA 18 Not Started
KAYA 1 Under Construction
KAYA 2 Under Construction
KAYA 3 Under Construction
KAYA 4 Under Construction
KAYA 5 Under Construction
KAYA 6 Under Construction
KAYA 7 Under Construction
KAYA 8 Under Construction
KAYA 9 Under Construction
KAYA 10 Under Construction
KAYA 11 Not Started
KAYA 12 Not Started
KAYA 13 Not Started
KAYA 14 Not Started
KAYA 15 Not Started
KAYA 16 Not Started
KAYA 17 Not Started
KAYA 18 Not Started
YUNA 1 Under Construction
YUNA 2 Under Construction
YUNA 3 Under Construction
YUNA 4 Under Construction
YUNA 5 Under Construction
YUNA 6 Under Construction
YUNA 7 Under Construction
YUNA 8 Under Construction
YUNA 9 Under Construction
YUNA 10 Under Construction
YUNA 11 Under Construction
YUNA 12 Not Started
YUNA 13 Not Started
YUNA 14 Not Started
YUNA 15 Not Started
YUNA 16 Not Started
YUNA 17 Not Started
YUNA 18 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 TOWER - KAYA
2 TOWER - YUNA
3 TOWER - SANA

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Building_Slab Casting_Construction Stage

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 10-01-2023 17-10-2023 17-10-2023
Fire NOC 03-11-2021 22-11-2021 22-11-2021 WBFES/TEC/NB/116/22
Permission from Water and Sewerage department 10-11-2022 10-01-2023 10-01-2023
Height clearance from Airport Authority of India (if any) 15-01-2021 29-04-2021 29-04-2021
Consent to Establish and Operate 30-10-2023 24-11-2023 24-11-2023
Other 16-11-2022 16-11-2022 16-11-2022