WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

MAGNOLIA NAKSHATRA PHASE-3

Project Status as on Quarter ending 30-06-2024
Updated as on 22-07-2024

Booking Status

  • Residential Apartments Booked
    119

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    16

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
A 1 Completed With CC
A 2 Completed With CC
A 3 Completed With CC
A 4 Completed With CC
B 1 Completed With CC
B 2 Completed With CC
B 3 Completed With CC
B 4 Completed With CC
C 1 Completed With CC
C 2 Completed With CC
C 3 Completed With CC
C 4 Completed With CC
D 1 Completed With CC
D 2 Completed With CC
D 3 Completed With CC
D 4 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Extinguisher Facility
2 Electrical Installation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Lift
2 Completed With CC Lobby
3 Completed With CC Roof
4 Completed With CC Septic Tank
5 Completed With CC Overhead Tank
6 Completed With CC Under Ground Water Reservoir

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download