New Please be informed that the last date for Quarterly Update of Registered Projects has been extended as per the order enclosed herewith. Click here to view the order ;  All promoters are directed to comply with the order of WBRERA vide no. 1986-RERA/L-01/2023 dated 06.12.2024 regarding Quarterly Update of Registered Projects and other instructions mentioned in the said order. Click here to view the order

Nexo & Parichay

Project Status as on Quarter ending 31-12-2024
Updated as on 03-01-2025

Booking Status

  • Residential Apartments Booked
    2

  • Commercial Unit Booked
    2

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    2

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Nexo - Lower Ground to 6th Floor - Commercial 1 Under Construction
Nexo - Lower Ground to 6th Floor - Commercial 2 Not Started
Nexo - Lower Ground to 6th Floor - Commercial 3 Not Started
Nexo - Lower Ground to 6th Floor - Commercial 4 Not Started
Nexo - Lower Ground to 6th Floor - Commercial 5 Not Started
Nexo - Lower Ground to 6th Floor - Commercial 6 Not Started
Nexo - Lower Ground to 6th Floor - Commercial 7 Not Started
Parichay - 1st to 7th Floor - Residential 1 Under Construction
Parichay - 1st to 7th Floor - Residential 2 Not Started
Parichay - 1st to 7th Floor - Residential 3 Not Started
Parichay - 1st to 7th Floor - Residential 4 Not Started
Parichay - 1st to 7th Floor - Residential 5 Not Started
Parichay - 1st to 7th Floor - Residential 6 Not Started
Parichay - 1st to 7th Floor - Residential 7 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Fire Fighting Facility
4 CCTV Facility
5 Power Backup/DG Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Entrance
2 Not Started Lobby
3 Not Started Staircase
4 Not Started Terrace
5 Not Started Lift

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download