New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

S V SUNSHINE APARTMENT

Project Status as on Quarter ending 31-12-2025
Updated as on 03-01-2026

Booking Status

  • Residential Apartments Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Not Started
1 2 Not Started
1 3 Not Started
1 4 Not Started
1 5 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Stairs
2 Lift
3 Lobby
4 Septic Tank
5 Fire Fighting Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Stairs
2 Not Started Lift
3 Not Started Lobby
4 Not Started Septic Tank
5 Not Started Overhead Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download