WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

URBANA PHASE II

Project Status as on Quarter ending 30-09-2023
Updated as on 14-10-2024

Booking Status

  • Residential Apartments Booked
    482

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    770

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
8 1 Under Construction
8 2 Under Construction
8 3 Under Construction
8 4 Under Construction
8 5 Under Construction
8 6 Under Construction
8 7 Under Construction
8 8 Under Construction
8 9 Under Construction
8 10 Under Construction
8 11 Under Construction
8 12 Under Construction
8 13 Under Construction
8 14 Under Construction
8 15 Under Construction
8 16 Under Construction
8 17 Under Construction
8 18 Under Construction
8 19 Under Construction
8 20 Under Construction
8 21 Under Construction
8 22 Under Construction
8 23 Under Construction
8 24 Under Construction
8 25 Under Construction
8 26 Under Construction
8 27 Under Construction
8 28 Under Construction
8 29 Under Construction
8 30 Under Construction
8 31 Under Construction
8 32 Under Construction
8 33 Under Construction
8 34 Under Construction
8 35 Under Construction
8 36 Under Construction
8 37 Under Construction
8 38 Under Construction
8 39 Under Construction
8 40 Under Construction
8 41 Under Construction
8 42 Under Construction
9 1 Under Construction
9 2 Under Construction
9 3 Under Construction
9 4 Under Construction
9 5 Under Construction
9 6 Under Construction
9 7 Under Construction
9 8 Under Construction
9 9 Under Construction
9 10 Under Construction
9 11 Under Construction
9 12 Under Construction
9 13 Under Construction
9 14 Under Construction
9 15 Under Construction
9 16 Under Construction
9 17 Under Construction
9 18 Under Construction
9 19 Under Construction
9 20 Under Construction
9 21 Under Construction
9 22 Under Construction
9 23 Under Construction
9 24 Under Construction
9 25 Under Construction
9 26 Under Construction
9 27 Under Construction
9 28 Under Construction
9 29 Under Construction
9 30 Under Construction
9 31 Under Construction
9 32 Under Construction
9 33 Under Construction
9 34 Under Construction
9 35 Under Construction
9 36 Under Construction
9 37 Under Construction
9 38 Under Construction
9 39 Not Started
9 40 Not Started
9 41 Not Started
9 42 Not Started
10 1 Under Construction
10 2 Under Construction
10 3 Under Construction
10 4 Under Construction
10 5 Under Construction
10 6 Under Construction
10 7 Under Construction
10 8 Under Construction
10 9 Under Construction
10 10 Under Construction
10 11 Under Construction
10 12 Under Construction
10 13 Under Construction
10 14 Under Construction
10 15 Under Construction
10 16 Under Construction
10 17 Under Construction
10 18 Under Construction
10 19 Under Construction
10 20 Under Construction
10 21 Under Construction
10 22 Under Construction
10 23 Under Construction
10 24 Under Construction
10 25 Under Construction
10 26 Under Construction
10 27 Under Construction
10 28 Under Construction
10 29 Under Construction
10 30 Under Construction
10 31 Under Construction
10 32 Under Construction
10 33 Under Construction
10 34 Under Construction
10 35 Under Construction
10 36 Under Construction
10 37 Under Construction
10 38 Under Construction
10 39 Under Construction
10 40 Under Construction
10 41 Under Construction
10 42 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities
2 Water Facility
3 Batching Plant

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Club
2 Completed With CC Power Backup
3 Under Construction Stairs
4 Under Construction Lift
5 Under Construction Lobby
6 Not Started Roof
7 Completed With CC Water Reservior With Treatment Plant
8 Completed With CC Septic Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download