New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

URBANA PHASE II

Project Status as on Quarter ending 31-12-2025
Updated as on 07-01-2026

Booking Status

  • Residential Apartments Booked
    511

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    819

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
8 1 Under Construction
8 2 Under Construction
8 3 Under Construction
8 4 Under Construction
8 5 Under Construction
8 6 Under Construction
8 7 Under Construction
8 8 Under Construction
8 9 Under Construction
8 10 Under Construction
8 11 Under Construction
8 12 Under Construction
8 13 Under Construction
8 14 Under Construction
8 15 Under Construction
8 16 Under Construction
8 17 Under Construction
8 18 Under Construction
8 19 Under Construction
8 20 Under Construction
8 21 Under Construction
8 22 Under Construction
8 23 Under Construction
8 24 Under Construction
8 25 Under Construction
8 26 Under Construction
8 27 Under Construction
8 28 Under Construction
8 29 Under Construction
8 30 Under Construction
8 31 Under Construction
8 32 Under Construction
8 33 Under Construction
8 34 Under Construction
8 35 Under Construction
8 36 Under Construction
8 37 Under Construction
8 38 Under Construction
8 39 Under Construction
8 40 Under Construction
8 41 Under Construction
8 42 Under Construction
9 1 Under Construction
9 2 Under Construction
9 3 Under Construction
9 4 Under Construction
9 5 Under Construction
9 6 Under Construction
9 7 Under Construction
9 8 Under Construction
9 9 Under Construction
9 10 Under Construction
9 11 Under Construction
9 12 Under Construction
9 13 Under Construction
9 14 Under Construction
9 15 Under Construction
9 16 Under Construction
9 17 Under Construction
9 18 Under Construction
9 19 Under Construction
9 20 Under Construction
9 21 Under Construction
9 22 Under Construction
9 23 Under Construction
9 24 Under Construction
9 25 Under Construction
9 26 Under Construction
9 27 Under Construction
9 28 Under Construction
9 29 Under Construction
9 30 Under Construction
9 31 Under Construction
9 32 Under Construction
9 33 Under Construction
9 34 Under Construction
9 35 Under Construction
9 36 Under Construction
9 37 Under Construction
9 38 Under Construction
9 39 Under Construction
9 40 Under Construction
9 41 Under Construction
9 42 Under Construction
10 1 Under Construction
10 2 Under Construction
10 3 Under Construction
10 4 Under Construction
10 5 Under Construction
10 6 Under Construction
10 7 Under Construction
10 8 Under Construction
10 9 Under Construction
10 10 Under Construction
10 11 Under Construction
10 12 Under Construction
10 13 Under Construction
10 14 Under Construction
10 15 Under Construction
10 16 Under Construction
10 17 Under Construction
10 18 Under Construction
10 19 Under Construction
10 20 Under Construction
10 21 Under Construction
10 22 Under Construction
10 23 Under Construction
10 24 Under Construction
10 25 Under Construction
10 26 Under Construction
10 27 Under Construction
10 28 Under Construction
10 29 Under Construction
10 30 Under Construction
10 31 Under Construction
10 32 Under Construction
10 33 Under Construction
10 34 Under Construction
10 35 Under Construction
10 36 Under Construction
10 37 Under Construction
10 38 Under Construction
10 39 Under Construction
10 40 Under Construction
10 41 Under Construction
10 42 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities
2 Water Facility
3 Batching Plant
4 Compacter Station
5 Emergency Evacuation
6 Electrical Facility
7 HVAC Facility
8 Substation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Club
2 Completed With CC Power Backup
3 Under Construction Stairs
4 Under Construction Lift
5 Under Construction Lobby
6 Under Construction Roof
7 Completed With CC Water Reservior With Treatment Plant
8 Completed With CC Sewerage Treatment Plant
9 Under Construction Overhead Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download