New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

SOUTHWINDS (PHASE-III)

Project Status as on Quarter ending 31-03-2023
Updated as on 14-04-2025

Booking Status

  • Residential Apartments Booked
    195

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    34

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 9; Residential 1 Completed With CC
Block 9; Residential 2 Completed With CC
Block 9; Residential 3 Completed With CC
Block 9; Residential 4 Completed With CC
Block 9; Residential 5 Completed With CC
Block 9; Residential 6 Completed With CC
Block 9; Residential 7 Completed With CC
Block 9; Residential 8 Completed With CC
Block 9; Residential 9 Completed With CC
Block 9; Residential 10 Completed With CC
Block 9; Residential 11 Completed With CC
Block 9; Residential 12 Completed With CC
Block 9; Residential 13 Completed With CC
Block 9; Residential 14 Completed With CC
Block 9; Residential 15 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Infrastructure
2 water facilities
3 fire and fighting

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Common Area
2 Completed With CC lobby
3 Completed With CC stairs
4 Completed With CC lift
5 Completed With CC roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download