WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

SOUTHWINDS (PHASE-III)

Project Status as on Quarter ending 31-12-2023
Updated as on 16-01-2024

Booking Status

  • Residential Apartments Booked
    195

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    34

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 9; Residential 1 Completed With CC
Block 9; Residential 2 Completed With CC
Block 9; Residential 3 Completed With CC
Block 9; Residential 4 Completed With CC
Block 9; Residential 5 Completed With CC
Block 9; Residential 6 Completed With CC
Block 9; Residential 7 Completed With CC
Block 9; Residential 8 Completed With CC
Block 9; Residential 9 Completed With CC
Block 9; Residential 10 Completed With CC
Block 9; Residential 11 Completed With CC
Block 9; Residential 12 Completed With CC
Block 9; Residential 13 Completed With CC
Block 9; Residential 14 Completed With CC
Block 9; Residential 15 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Infrastructure
2 water facilities
3 fire and fighting

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Common Area
2 Completed With CC lobby
3 Completed With CC stairs
4 Completed With CC lift
5 Completed With CC roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download