WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

BASUNDHARA

Project Status as on Quarter ending 31-03-2025
Updated as on 31-01-2025

Booking Status

  • Residential Apartments Booked
    5

  • Commercial Unit Booked
    3

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    2

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK 1 1 Completed With CC
BLOCK 1 2 Completed With CC
BLOCK 1 3 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 EXCAVATION
2 SLAB STRACTURE
3 INTERNAL WALLS,INTERNAL PLASTER,FLOORING
4 STAIR CASE ,LIFT WELLS AND LOBBIES
5 EXTERNAL PLUMBING AND EXTERNAL PLASTER,ELEVATION
6 STAIR CASE ,LIFT WELLS AND LOBBIES

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC INTERNAL ROADS & FOOTPATH
2 Completed With CC WATER SUPPLY
3 Completed With CC TERRACE
4 Under Construction ELECTRICAL METER
5 Completed With CC SEWAGE
6 Completed With CC WATER TANK

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download