SOUTHWINDS (PHASE V)

Project Status as on Quarter ending 31-03-2024
Updated as on 06-04-2024

Booking Status

  • Residential Apartments Booked
    164

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    48

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
11 1 Completed With CC
11 2 Completed With CC
11 3 Completed With CC
11 4 Completed With CC
11 5 Completed With CC
11 6 Completed With CC
11 7 Completed With CC
11 8 Completed With CC
11 9 Completed With CC
11 10 Completed With CC
11 11 Completed With CC
11 12 Completed With CC
11 13 Completed With CC
12 1 Completed With CC
12 2 Completed With CC
12 3 Completed With CC
12 4 Completed With CC
12 5 Completed With CC
12 6 Completed With CC
12 7 Completed Without CC
12 8 Completed With CC
12 9 Completed With CC
12 10 Completed With CC
12 11 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Facility
2 Fire Facility
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Stairs
2 Completed With CC Lift
3 Completed With CC Roof
4 Completed With CC Lobby

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Other 29-05-2023 29-05-2023 29-05-2023 LICENSE TO WORK A LIFT BLOCK - 11
Such other approvals as may be required and obtained for the project 18-05-2029 18-05-2029 18-05-2029 License to work a lift for block - 12