Booking Status

  • Residential Apartments Booked
    430

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    70

  • Mechanical Parking Booked
    309

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block - 13 - Residential 5 Under Construction
Block - 13 - Residential 6 Under Construction
Block - 13 - Residential 7 Under Construction
Block - 13 - Residential 8 Under Construction
Block - 13 - Residential 9 Under Construction
Block - 13 - Residential 10 Under Construction
Block - 13 - Residential 11 Under Construction
Block - 13 - Residential 12 Under Construction
Block - 13 - Residential 13 Under Construction
Block - 13 - Residential 14 Under Construction
Block - 13 - Residential 15 Under Construction
Block - 13 - Residential 16 Under Construction
Block - 13 - Residential 17 Under Construction
Block - 13 - Residential 18 Under Construction
Block - 14 - Residential 1 Under Construction
Block - 14 - Residential 2 Under Construction
Block - 14 - Residential 3 Under Construction
Block - 14 - Residential 4 Under Construction
Block - 14 - Residential 5 Under Construction
Block - 14 - Residential 6 Under Construction
Block - 14 - Residential 7 Under Construction
Block - 14 - Residential 8 Under Construction
Block - 14 - Residential 9 Under Construction
Block - 14 - Residential 10 Under Construction
Block - 14 - Residential 11 Under Construction
Block - 14 - Residential 12 Under Construction
Block - 14 - Residential 13 Under Construction
Block - 14 - Residential 14 Under Construction
Block - 14 - Residential 15 Under Construction
Block - 14 - Residential 16 Under Construction
Block - 14 - Residential 17 Under Construction
Block - 14 - Residential 18 Under Construction
Block -15 - Residential 1 Under Construction
Block -15 - Residential 2 Under Construction
Block -15 - Residential 3 Under Construction
Block -15 - Residential 4 Under Construction
Block -15 - Residential 5 Under Construction
Block -15 - Residential 6 Under Construction
Block -15 - Residential 7 Under Construction
Block -15 - Residential 8 Under Construction
Block -15 - Residential 9 Under Construction
Block -15 - Residential 10 Under Construction
Block -15 - Residential 11 Under Construction
Block -15 - Residential 12 Under Construction
Block -15 - Residential 13 Under Construction
Block -15 - Residential 14 Under Construction
Block -15 - Residential 15 Under Construction
Block -15 - Residential 16 Under Construction
Block -15 - Residential 17 Under Construction
Block -15 - Residential 18 Under Construction
Block - 16 - Residential 1 Under Construction
Block - 16 - Residential 2 Under Construction
Block - 16 - Residential 3 Under Construction
Block - 16 - Residential 4 Under Construction
Block - 16 - Residential 5 Under Construction
Block - 16 - Residential 6 Under Construction
Block - 16 - Residential 7 Under Construction
Block - 16 - Residential 8 Under Construction
Block - 16 - Residential 9 Under Construction
Block - 16 - Residential 10 Under Construction
Block - 16 - Residential 11 Under Construction
Block - 16 - Residential 12 Under Construction
Block - 16 - Residential 13 Under Construction
Block - 16 - Residential 14 Under Construction
Block - 16 - Residential 15 Under Construction
Block - 16 - Residential 16 Under Construction
Block - 16 - Residential 17 Under Construction
Block - 16 - Residential 18 Under Construction
Block - 13 - Residential 1 Under Construction
Block - 13 - Residential 2 Under Construction
Block - 13 - Residential 3 Under Construction
Block - 13 - Residential 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Fire Fighting Facilty
4 Use of Renewable Energy

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Area
2 Under Construction Lobby
3 Under Construction Stairs
4 Under Construction Lift
5 Under Construction Roof
6 Under Construction Entrance

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 03-09-2024 03-09-2024 03-09-2024
Other 04-10-2024 04-10-2024 04-10-2024