WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

VOLT

Project Status as on Quarter ending 31-12-2020
Updated as on 02-03-2021

Booking Status

  • Commercial Unit Booked
    43

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    54

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 5 Under Construction
1 4 Under Construction
1 3 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 COMBINED PILE CAP CASTING DONE
2 SOILING,PCC,BRICK SHUTTERING
3 DECK SLAB -1
4 DECK SLAB -2
5 DECK SLAB-3

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction support str
2 Under Construction excavation
3 Under Construction staircase

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download