Solaris Shalimar Phase 1C

Project Status as on Quarter ending 31-03-2025
Updated as on 24-03-2025

Booking Status

  • Residential Apartments Booked
    332

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    80

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 6 2 Under Construction
Tower 6 3 Under Construction
Tower 6 4 Not Started
Tower 6 5 Not Started
Tower 6 6 Not Started
Tower 6 7 Not Started
Tower 6 8 Not Started
Tower 6 9 Not Started
Tower 6 10 Not Started
Tower 6 11 Not Started
Tower 6 12 Not Started
Tower 6 13 Not Started
Tower 6 14 Not Started
Tower 6 15 Not Started
Tower 6 16 Not Started
Tower 6 17 Not Started
Tower 6 18 Not Started
Tower 6 19 Not Started
Tower 7 2 Under Construction
Tower 7 3 Not Started
Tower 7 4 Not Started
Tower 7 5 Not Started
Tower 7 6 Not Started
Tower 7 7 Not Started
Tower 7 8 Not Started
Tower 7 9 Not Started
Tower 7 10 Not Started
Tower 7 11 Not Started
Tower 7 12 Not Started
Tower 7 13 Not Started
Tower 7 14 Not Started
Tower 7 15 Not Started
Tower 7 16 Not Started
Tower 7 17 Not Started
Tower 7 18 Not Started
Tower 7 19 Not Started
Tower 6 1 Under Construction
Tower 7 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 09-08-2021 09-03-2022 19-09-2022
Height clearance from Airport Authority of India (if any) 10-01-2022 10-05-2022 30-05-2022
Other 22-05-2024 22-05-2024 22-05-2024