New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

DIVYA JYOTI

Project Status as on Quarter ending 31-03-2021
Updated as on 07-01-2026

Booking Status

  • Residential Apartments Booked
    76

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    46

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block-A 1 Completed With CC
Block-A 2 Completed With CC
Block-A 3 Completed With CC
Block-A 4 Completed With CC
Block-A 5 Completed With CC
Block-A 6 Completed With CC
Block-B 1 Completed With CC
Block-B 2 Completed With CC
Block-B 3 Completed With CC
Block-B 4 Completed With CC
Block-B 5 Completed With CC
Block-B 6 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Fire Fighting Facility
3 Emergency Evacuation Services

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Lobby
2 Completed With CC Stairs
3 Completed With CC Lift
4 Completed With CC Roof
5 Completed With CC Power Backup
6 Completed With CC Security Services
7 Completed With CC Fitness Center
8 Completed With CC Community Center

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download