Project Status as on Quarter ending 31-03-2021
Updated as on 01-04-2021

Booking Status

  • Residential Apartments Booked
    6

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    7

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Stand-alone Building G+4 1 Under Construction
Stand-alone Building G+4 2 Under Construction
Stand-alone Building G+4 3 Under Construction
Stand-alone Building G+4 4 Under Construction
Stand-alone Building G+4 2 Under Construction
Stand-alone Building G+4 3 Under Construction
Stand-alone Building G+4 2 Under Construction
Stand-alone Building G+4 2 Under Construction
Stand-alone Building G+4 2 Under Construction
Stand-alone Building G+4 3 Under Construction
Stand-alone Building G+4 4 Under Construction
Stand-alone Building G+4 4 Completed With CC
Stand-alone Building G+4 4 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Plaster work going on
2 external structure and sewerage work
3 elevation and sewerage worj
4 WINDOW FITTING
5 Completion Certificate received from KMC dated 02.03.2021
6 Kitchen Area
7 Wash-room Area

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Not Started
2 Under Construction External Wall- Plaster
3 Under Construction staircase,building electrical duct & lift door
4 Completed With CC Stair Lobby

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Other 10-12-2020 27-04-2020 08-01-2021