Project Status as on Quarter ending 30-09-2024
Updated as on 03-10-2024

Booking Status

  • Residential Apartments Booked
    49

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    20

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 - Residential - 2nd Floor - 11th Floor 11 Completed With CC
Block 1 - Commercial - 1st Floor 1 Completed With CC
Block 1 - Commercial - Ground 1 Completed With CC
Block 1 - Residential - 2nd Floor - 11th Floor 2 Completed With CC
Block 1 - Residential - 2nd Floor - 11th Floor 3 Completed With CC
Block 1 - Residential - 2nd Floor - 11th Floor 4 Completed With CC
Block 1 - Residential - 2nd Floor - 11th Floor 5 Completed With CC
Block 1 - Residential - 2nd Floor - 11th Floor 6 Completed With CC
Block 1 - Residential - 2nd Floor - 11th Floor 7 Completed With CC
Block 1 - Residential - 2nd Floor - 11th Floor 8 Completed With CC
Block 1 - Residential - 2nd Floor - 11th Floor 9 Completed With CC
Block 1 - Residential - 2nd Floor - 11th Floor 10 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Facility
2 Emergency Evacuation
3 Renewable Energy
4 Water Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Lobby
2 Completed With CC Stairs
3 Completed With CC LIft
4 Completed With CC Roof
5 Completed With CC Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download