New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     Applications are invited from the eligible and willing persons for the position of (i) Judicial Member of West Bengal Real Estate Appellate Tribunal (WBREAT) and (ii) Member of West Bengal Real Estate Regulatory Authority (WBRERA) Click here to open;    

ADI GURU RESIDENCY

Project Status as on Quarter ending 31-12-2025
Updated as on 31-12-2025

Booking Status

  • Residential Apartments Booked
    1

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Block II- work in progress. Roof casting completed. Brick & plaster work is going on. Putty & tiles work is pending Electrical & plumbing work is going on
2 Block II- work in progress. Roof casting completed. Brick & plaster work is going on. Putty & tiles work is pending Electrical & plumbing work is going on.
3 For Block 2: Roof casting, brick work, inside and outside plaster, Putty work, Flooring work incl passage flooring work completed. Sliding work for 1st and 2nd floor completed. Passage and roof finishing work is pending
4 For Block 1: Roof casting, brick work, Inside and Outside plaster work completed. Putty and Marble work in progress
5 Block 1 work has been started
6 basement work for Block 1 completed
7 Block 2 work in progress
8 Excavation done. Plinth level completed. Roof casting done for BLOCK 2. For BLOCK 1 work not started
9 Block 2 Plastering work in progress
10 Internal electricity work in progress

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Work in progress. Block I yet to start
2 Under Construction Few area work is under progress
3 Under Construction Work in progress for Block 2. For Block 1 work not started
4 Under Construction Septic tank work in progress
5 Under Construction Water connection work in prgress

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download