WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

SONARCITY -PHASE I

Project Status as on Quarter ending 31-03-2024
Updated as on 03-04-2024

Booking Status

  • Residential Apartments Booked
    426

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    391

  • Mechanical Parking Booked
    69

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 1 Completed With CC
Block 1 2 Completed With CC
Block 1 3 Completed With CC
Block 1 4 Completed With CC
Block 1 5 Completed With CC
Block 1 6 Completed With CC
Block 1 7 Completed With CC
Block 1 8 Completed With CC
Block 1 9 Completed With CC
Block 1 10 Completed With CC
Block 1 11 Completed With CC
Block 2 1 Completed With CC
Block 2 2 Completed With CC
Block 2 3 Completed With CC
Block 2 4 Completed With CC
Block 2 5 Completed With CC
Block 2 6 Completed With CC
Block 2 7 Completed With CC
Block 2 8 Completed With CC
Block 2 9 Completed With CC
Block 2 10 Completed With CC
Block 2 11 Completed With CC
Block 3 1 Completed With CC
Block 3 2 Completed With CC
Block 3 3 Completed With CC
Block 3 4 Completed With CC
Block 3 5 Completed With CC
Block 3 6 Completed With CC
Block 3 7 Completed With CC
Block 3 8 Completed With CC
Block 3 9 Completed With CC
Block 3 10 Completed With CC
Block 3 11 Completed With CC
Block 3 12 Completed With CC
Block 7 1 Completed With CC
Block 7 2 Completed With CC
Block 7 3 Completed With CC
Block 7 4 Completed With CC
Block 7 5 Completed With CC
Block 7 6 Completed With CC
Block 7 7 Completed With CC
Block 7 8 Completed With CC
Block 7 9 Completed With CC
Block 7 10 Completed With CC
Block 7 11 Completed With CC
Block 7 12 Completed With CC
Block 8 1 Completed With CC
Block 8 2 Completed With CC
Block 8 3 Completed With CC
Block 8 4 Completed With CC
Block 8 5 Completed With CC
Block 8 6 Completed With CC
Block 8 7 Completed With CC
Block 8 8 Completed With CC
Block 8 9 Completed With CC
Block 8 10 Completed With CC
Block 8 11 Completed With CC
Block 8 12 Completed With CC
Block 14 1 Completed With CC
Block 14 2 Completed With CC
Block 14 3 Completed With CC
Block 14 4 Completed With CC
Block 20 1 Completed With CC
Block 20 2 Completed With CC
Block 20 3 Completed With CC
Block 20 4 Completed With CC
Block 20 5 Completed With CC
Block 20 6 Completed With CC
Block 20 7 Completed With CC
Block 20 8 Completed With CC
Block 20 9 Completed With CC
Block 20 10 Completed With CC
Block 20 11 Completed With CC
Block 20 12 Completed With CC
Block 21 1 Completed With CC
Block 21 2 Completed With CC
Block 21 3 Completed With CC
Block 21 4 Completed With CC
Block 21 5 Completed With CC
Block 21 6 Completed With CC
Block 21 7 Completed With CC
Block 21 8 Completed With CC
Block 21 9 Completed With CC
Block 21 10 Completed With CC
Block 21 11 Completed With CC
Block 21 12 Completed With CC
Block 22 1 Completed With CC
Block 22 2 Completed With CC
Block 22 3 Completed With CC
Block 22 4 Completed With CC
Block 22 5 Completed With CC
Block 22 6 Completed With CC
Block 22 7 Completed With CC
Block 22 8 Completed With CC
Block 22 9 Completed With CC
Block 22 10 Completed With CC
Block 22 11 Completed With CC
Block 22 12 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Supply
2 Fire Extinguisher
3 Emergency Evacuation
4 Block 8- 1st Phase Plaster, Floor Tiles, Toilet Walls, Kitchen Counter, Fire MS Riser Pipe, Aluminium Window
5 Block 20-Toilet Plumbing, Plumbing Work, Electrical Work, Plaster, Garage Railing, Fire MS Riser Pipe
6 Block 21-Toilet Plumbing, Plumbing Work, Electrical Work, Plaster, Garage Railing, Fire MS Riser Pipe
7
8
9
10 Block- 1 Internal Putty , Flooring, Electric conduct Wire, Aluminium Window, Balcony Railing, Fire Door, Fire Pipe, Flush Door, Kitchen Counter, Lift Facia, Stair Railing., Block - 1
11 Block 2- Internal Putty , Flooring, Electric conduct Wire, Aluminium Window, Balcony Railing, Fire Door, Fire Pipe, Flush Door, Kitchen Counter, Lift Facia, Stair Railing., Block - 2
12 Block 3- Aluminium Window, Marble Flooring, Stair Marble And Flooring, Toilet Wall Tiles, Fire MS Riser , Ground Floor PCC
13 Block 7- 1st Phase Plaster, Floor Tiles, Toilet Walls, Kitchen Counter, Fire MS Riser Pipe
14 Block 22-Toilet Plumbing, Plumbing Work, Electrical Work, Plaster, Garage Railing, Fire MS Riser Pipe

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lobby
2 Under Construction Stairs
3 Not Started Lift
4 Not Started Roof
5 Under Construction POND
6 Under Construction Road
7 Under Construction STP Behind Tower 3
8 Under Construction Under Groung Water Reservoir

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download