New Please be informed that the The last date for submission of Quarterly Update of Registered Real Estate Projects is hereby extended tillĀ 28.02.2025 as per the order enclosed herewith. Click here to view the order ;  All promoters are directed to comply with the order of WBRERA vide no. 1986-RERA/L-01/2023 dated 06.12.2024 regarding Quarterly Update of Registered Projects and other instructions mentioned in the said order. Click here to view the order

Uttora Phase E2

Project Status as on Quarter ending 31-12-2024
Updated as on 07-01-2025

Booking Status

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 PLOTTED DEVELOPMENT
2 PLOTTED DEVELOPMENT
3 PLOTTED DEVELOPMENT
4 PLOTTED DEVELOPMENT
5 Completed
6 Plot Development

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC plotted development
2 Completed With CC completed
3 Under Construction CLUSTER ROAD, PIPELINE FOR STP UPTO PLOT HEAD, STREET LIGHT, WATER TANK ETC.
4 Under Construction Street Light and Electrical Cable line etc 70% complete
5 Under Construction Horticulture 60% completed

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download