New Please be informed that the last date for Quarterly Update of Registered Projects has been extended as per the order enclosed herewith. Click here to view the order ;  All promoters are directed to comply with the order of WBRERA vide no. 1986-RERA/L-01/2023 dated 06.12.2024 regarding Quarterly Update of Registered Projects and other instructions mentioned in the said order. Click here to view the order

57, PRATAP GARH

Project Status as on Quarter ending 31-12-2023
Updated as on 24-12-2024

Booking Status

  • Residential Apartments Booked
    4

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    3

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Completed With CC
1 2 Completed With CC
1 3 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download