WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Solaris Joka Phase 2

Project Status as on Quarter ending 31-03-2024
Updated as on 06-03-2024

Booking Status

  • Residential Apartments Booked
    209

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    57

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1
2 Internal Infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 03-12-2021 03-06-2022 17-06-2022
Consent to Establish and Operate 21-06-2022 21-07-2022 15-07-2022
Other 08-09-2021 24-09-2021 01-10-2021