WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Swapnabhumi V

Project Status as on Quarter ending 31-03-2024
Updated as on 02-04-2024

Booking Status

  • Residential Apartments Booked
    17

  • Commercial Unit Booked
    4

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    19

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 - Ground Floor - Commercial 1 Under Construction
Block 1 - 1st to 6th - Residencial 1 Under Construction
Block 1 - 1st to 6th - Residencial 2 Under Construction
Block 1 - 1st to 6th - Residencial 3 Under Construction
Block 1 - 1st to 6th - Residencial 4 Under Construction
Block 1 - 1st to 6th - Residencial 5 Under Construction
Block 1 - 1st to 6th - Residencial 6 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Emergency Evacuation
2 Water Facilities
3 Fire Facilities

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lobby
2 Under Construction Staircase
3 Under Construction lift
4 Under Construction Roof
5 Under Construction Septic Tank
6 Under Construction Power Back up

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download