WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

BEAUMONDE PHASE-II

Project Status as on Quarter ending 31-03-2024
Updated as on 03-04-2024

Booking Status

  • Residential Apartments Booked
    52

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    103

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower B 1 Under Construction
Tower B 2 Not Started
Tower B 3 Not Started
Tower B 4 Not Started
Tower B 4 Not Started
Tower B 5 Not Started
Tower B 6 Not Started
Tower B 7 Not Started
Tower B 8 Not Started
Tower B 9 Not Started
Tower B 10 Not Started
Tower B 11 Not Started
Tower B 12 Not Started
Tower B 13 Not Started
Tower B 14 Not Started
Tower B 15 Not Started
Tower B 16 Not Started
Tower B 17 Not Started
Tower B 18 Not Started
Tower B 19 Not Started
Tower B 20 Not Started
Tower B 21 Not Started
Tower B 22 Not Started
Tower B 23 Not Started
Tower B 24 Not Started
Tower D 1 Under Construction
Tower D 2 Not Started
Tower D 3 Not Started
Tower D 4 Not Started
Tower D 5 Not Started
Tower D 6 Not Started
Tower D 7 Not Started
Tower D 8 Not Started
Tower D 9 Not Started
Tower D 10 Not Started
Tower D 11 Not Started
Tower D 12 Not Started
Tower D 13 Not Started
Tower D 14 Not Started
Tower D 15 Not Started
Tower D 16 Not Started
Tower D 17 Not Started
Tower D 18 Not Started
Tower D 19 Not Started
Tower D 20 Not Started
Tower D 21 Not Started
Tower D 22 Not Started
Tower D 23 Not Started
Tower D 24 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Facility
2 Fire Facility
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Lobby
2 Staircase
3 Lift
4 Roof
5 Septic Tank
6 Power Backup

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download