Project Status as on Quarter ending 30-09-2023
Updated as on 07-04-2024

Booking Status

  • Residential Apartments Booked
    368

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    326

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
HIG-1 1 Under Construction
HIG-1 2 Under Construction
HIG-1 3 Under Construction
HIG-1 4 Under Construction
HIG-1 5 Under Construction
HIG-1 6 Under Construction
HIG-1 7 Under Construction
HIG-1 8 Under Construction
HIG-1 9 Under Construction
HIG-1 10 Under Construction
HIG-1 11 Under Construction
HIG-1 12 Under Construction
HIG-1 13 Under Construction
HIG-1 14 Under Construction
HIG-1 15 Under Construction
HIG-1 16 Under Construction
HIG-2 1 Under Construction
HIG-2 2 Under Construction
HIG-2 3 Under Construction
HIG-2 4 Under Construction
HIG-2 5 Under Construction
HIG-2 6 Under Construction
HIG-2 7 Under Construction
HIG-2 8 Under Construction
HIG-2 9 Under Construction
HIG-2 10 Under Construction
HIG-2 11 Under Construction
HIG-2 12 Under Construction
HIG-2 13 Under Construction
HIG-2 14 Under Construction
HIG-2 15 Under Construction
HIG-2 16 Under Construction
HIG-3 1 Under Construction
HIG-3 2 Under Construction
HIG-3 3 Under Construction
HIG-3 4 Under Construction
HIG-3 5 Under Construction
HIG-3 6 Under Construction
HIG-3 7 Under Construction
HIG-3 8 Under Construction
HIG-3 9 Under Construction
HIG-3 10 Under Construction
HIG-3 11 Under Construction
HIG-3 12 Under Construction
HIG-3 13 Under Construction
HIG-3 14 Under Construction
HIG-3 15 Under Construction
HIG-3 16 Under Construction
LIG-1 1 Under Construction
LIG-1 2 Under Construction
LIG-1 3 Under Construction
LIG-1 4 Under Construction
LIG-2 1 Under Construction
LIG-2 2 Under Construction
LIG-2 3 Under Construction
LIG-2 4 Under Construction
MIG-1 1 Under Construction
MIG-1 2 Under Construction
MIG-1 3 Under Construction
MIG-1 4 Under Construction
MIG-1 5 Under Construction
MIG-1 6 Under Construction
MIG-1 7 Under Construction
MIG-1 8 Under Construction
MIG-1 9 Under Construction
MIG-1 10 Under Construction
MIG-1 11 Under Construction
MIG-1 12 Under Construction
MIG-1 13 Under Construction
MIG-2 1 Under Construction
MIG-2 2 Under Construction
MIG-2 3 Under Construction
MIG-2 4 Under Construction
MIG-2 5 Under Construction
MIG-2 6 Under Construction
MIG-2 7 Under Construction
MIG-2 8 Under Construction
MIG-2 9 Under Construction
MIG-2 10 Under Construction
MIG-2 11 Under Construction
MIG-2 12 Under Construction
MIG-2 13 Under Construction
MIG-3 1 Under Construction
MIG-3 2 Under Construction
MIG-3 3 Under Construction
MIG-3 4 Under Construction
MIG-3 5 Under Construction
MIG-3 6 Under Construction
MIG-3 7 Under Construction
MIG-3 8 Under Construction
MIG-3 9 Under Construction
MIG-3 10 Under Construction
MIG-3 11 Under Construction
MIG-3 12 Under Construction
MIG-3 13 Under Construction
BLOCK D 1 Under Construction
BLOCK D 2 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 FIRE FIGHTING FACILITY
2 DIESEL GENERATOR
3 SWIMMING POOL

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction LIFT
2 Under Construction STAIRS
3 Under Construction ROOF
4 Under Construction WATERHEAD TANK
5 Under Construction CLUB
6 Under Construction PLAY AREA
7 Under Construction Underground Water Reservoir

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download