Vanya Awas - Villas Phase - I

Project Status as on Quarter ending 31-03-2024
Updated as on 07-04-2024

Booking Status

  • Residential Apartments Booked
    58

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
EDEN (E-1) 1 Under Construction
EDEN (E-2) 1 Under Construction
EDEN (E-3) 1 Under Construction
EDEN (E-4) 1 Under Construction
EDEN (E-5) 1 Under Construction
EDEN (E-6) 1 Under Construction
EDEN (E-7) 1 Under Construction
EDEN (E-8) 1 Under Construction
EDEN (E-9) 1 Under Construction
EDEN (E-10) 1 Under Construction
EDEN (E-11) 1 Under Construction
EDEN (E-12) 1 Under Construction
EDEN (E-13) 1 Under Construction
EDEN (E-14) 1 Not Started
EDEN (E-15) 1 Under Construction
EDEN (E-16) 1 Not Started
EDEN (E-17) 1 Under Construction
EDEN (E-18) 1 Not Started
WILLOW (W-1) 1 Under Construction
WILLOW (W-2) 1 Under Construction
WILLOW (W-3) 1 Under Construction
WILLOW (W-4) 1 Under Construction
WILLOW (W-5) 1 Under Construction
WILLOW (W-6) 1 Under Construction
WILLOW (W-7) 1 Under Construction
WILLOW (W-8) 1 Under Construction
WILLOW (W-9) 1 Under Construction
WILLOW (W-10) 1 Under Construction
WILLOW (W-11) 1 Under Construction
WILLOW (W-12) 1 Not Started
WILLOW (W-13) 1 Under Construction
WILLOW (W-14) 1 Not Started
WILLOW (W-15) 1 Under Construction
WILLOW (W-16) 1 Not Started
SILVA (S-1) 1 Under Construction
SILVA (S-2) 1 Under Construction
SILVA (S-3) 1 Under Construction
SILVA (S-4) 1 Under Construction
SILVA (S-5) 1 Under Construction
SILVA (S-6) 1 Under Construction
SILVA (S-7) 1 Under Construction
SILVA (S-8) 1 Under Construction
SILVA (S-9) 1 Under Construction
SILVA (S-10) 1 Under Construction
SILVA (S-11) 1 Under Construction
SILVA (S-12) 1 Under Construction
SILVA (S-13) 1 Under Construction
SILVA (S-14) 1 Not Started
SILVA (S-15) 1 Under Construction
SILVA (S-160 1 Not Started
BROOK (B-1) 1 Under Construction
BROOK (B-2) 1 Under Construction
BROOK (B-3) 1 Under Construction
BROOK (B-4) 1 Under Construction
BROOK (B-5) 1 Under Construction
BROOK (B-6) 1 Under Construction
BROOK (B-7) 1 Under Construction
BROOK (B-8) 1 Not Started
BROOK (B-9) 1 Under Construction
BROOK (B-10) 1 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 WATER SUPPLY FROM BOREWELL
2 FIRE FIGHTING AND EMERGENCY EVACUATION PLAN

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started SEATING ALCOVE
2 Not Started SENIOR CITIZEN'S CORNER
3 Not Started PLAZA
4 Not Started LANDSCAPE AREAS
5 Not Started JUNGLE GYM
6 Not Started TRAMPOLINE PARK
7 Not Started YOGA LAWN

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Consent to Establish and Operate 18-02-2024 18-03-2024 18-03-2024