Adi And Avi Heights

Project Status as on Quarter ending 31-03-2024
Updated as on 02-04-2024

Booking Status

  • Residential Apartments Booked
    1

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    1

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block - 1st to 5th Floor - Residential 1 Under Construction
Block - 1st to 5th Floor - Residential 2 Not Started
Block - 1st to 5th Floor - Residential 3 Not Started
Block - 1st to 5th Floor - Residential 4 Not Started
Block - 1st to 5th Floor - Residential 5 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Fire Fighting Facilty

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lobby
2 Under Construction Stairs
3 Not Started lift
4 Not Started roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download