Booking Status

  • Residential Apartments Booked
    149

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    48

  • Mechanical Parking Booked
    30

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block - 1 1 Completed Without CC
Block - 1 2 Completed Without CC
Block - 1 4 Completed Without CC
Block - 1 3 Completed Without CC
Block - 1 5 Completed Without CC
Block - 1 6 Completed Without CC
Block - 1 7 Completed Without CC
Block - 1 8 Completed Without CC
Block - 1 9 Completed Without CC
Block - 1 10 Completed Without CC
Block - 1 11 Completed Without CC
Block - 1 12 Completed Without CC
Block-2 1 Completed Without CC
Block-2 2 Completed Without CC
Block-2 3 Completed Without CC
Block-2 4 Completed Without CC
Block-2 5 Completed Without CC
Block-2 6 Completed Without CC
Block-2 7 Completed Without CC
Block-2 8 Completed Without CC
Block-2 9 Completed Without CC
Block-2 10 Completed Without CC
Block-2 11 Completed Without CC
Block-2 12 Completed Without CC
Block - 3 1 Completed Without CC
Block - 3 2 Completed Without CC
Block - 3 3 Completed Without CC
Block - 3 4 Completed Without CC
Block - 3 5 Completed Without CC
Block - 3 6 Completed Without CC
Block - 3 7 Completed Without CC
Block - 3 8 Completed Without CC
Block - 3 9 Completed Without CC
Block - 3 10 Completed Without CC
Block - 3 11 Completed Without CC
Block - 3 12 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Facilities
2 Fire Facilities
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Ac Lounge
2 Completed Without CC Adda Corner
3 Completed Without CC Astronomical Deck
4 Completed Without CC Swimming Pool
5 Completed Without CC Creche 1
6 Completed Without CC Creche 2
7 Completed Without CC Entrance
8 Completed Without CC Tower 1 lift Lobby
9 Completed Without CC Gym
10 Completed Without CC Ladies & Gents Spa
11 Completed Without CC Tower 2 Lift Lobby
12 Completed Without CC Senior Citizen Corner 1
13 Completed Without CC Senior Citizen Corner 2
14 Completed Without CC Ground Floor Lawn
15 Completed Without CC Kids Play Area
16 Completed Without CC Yoga Deck
17 Completed Without CC Game Room
18 Completed Without CC Roof
19 Completed Without CC Exit Gate
20 Completed Without CC Community Hall
21 Completed Without CC Louge
22 Completed Without CC Open Gym
23 Completed Without CC Tower 3 Lift lobby
24 Completed Without CC Mechanical Parking

Approval for NOC