WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

NS AMARA

Project Status as on Quarter ending 31-03-2024
Updated as on 02-04-2024

Booking Status

  • Residential Apartments Booked
    55

  • Commercial Unit Booked
    21

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    53

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower - 2 - Residential 1 Under Construction
Tower - 2 - Residential 2 Under Construction
Tower - 2 - Residential 3 Under Construction
Tower - 2 - Residential 4 Under Construction
Tower - 2 - Residential 5 Not Started
Tower - 3 - Residential 1 Under Construction
Tower - 3 - Residential 2 Not Started
Tower - 3 - Residential 3 Not Started
Tower - 3 - Residential 4 Not Started
Tower - 3 - Residential 5 Not Started
Tower - 4 - Residential 1 Under Construction
Tower - 4 - Residential 2 Under Construction
Tower - 4 - Residential 3 Under Construction
Tower - 4 - Residential 4 Under Construction
Tower -1 -Commercial - Ground 1 Under Construction
Tower -1 -Commercial- 1st Floor 1 Under Construction
Tower 1 - Residential - 2nd to 5th Floor 2 Not Started
Tower 1 - Residential - 2nd to 5th Floor 3 Not Started
Tower 1 - Residential - 2nd to 5th Floor 4 Not Started
Tower 1 - Residential - 2nd to 5th Floor 5 Not Started
Tower - 4 - Residential 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Emergency Evacuation
2 Water Supply Facility
3 Fire Extinguisher Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Septic Tank
2 Not Started Power Backup
3 Under Construction Lobby
4 Under Construction Stairs
5 Under Construction Lift
6 Not Started Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 24-04-2023 24-07-2023 24-07-2023
Such other approvals as may be required and obtained for the project 04-03-2023 04-07-2023 04-07-2023