Project Status as on Quarter ending 31-03-2024
Updated as on 06-04-2024

Booking Status

  • Residential Apartments Booked
    66

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    28

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Wing 1 Phase 2 2 Under Construction
Wing 1 Phase 2 3 Under Construction
Wing 1 Phase 2 4 Not Started
Wing 1 Phase 2 5 Not Started
Wing 1 Phase 2 6 Not Started
Wing 1 Phase 2 7 Not Started
Wing 1 Phase 2 8 Not Started
Wing 1 Phase 2 9 Not Started
Wing 1 Phase 2 10 Not Started
Wing 1 Phase 2 11 Not Started
Wing 1 Phase 2 12 Not Started
Wing 1 Phase 2 13 Not Started
Wing 1 Phase 2 14 Not Started
Wing 1 Phase 2 15 Not Started
Wing 1 Phase 2 16 Not Started
Wing 1 Phase 2 17 Not Started
Wing 1 Phase 2 18 Not Started
Wing 1 Phase 2 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Fire Fighting Facilty
3 Use of Renewable Energy

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction lobby
2 Under Construction stairs
3 Not Started lift
4 Not Started roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download