WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

KAMALA DHAM PHASE - III

Project Status as on Quarter ending 31-03-2024
Updated as on 02-04-2024

Booking Status

  • Residential Apartments Booked
    26

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    14

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block -D 5 Under Construction
Block- E Ground 1 Under Construction
Block - E 2 Under Construction
Block - E 3 Under Construction
Block - E 4 Under Construction
Block - E 5 Under Construction
Block-D Ground 1 Under Construction
Block -D 1 Under Construction
Block -D 2 Under Construction
Block -D 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Emergency Evacuation
2 WATER FACILITES
3 FIRE AND FIGHTING

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Entrance
2 Under Construction Septic Tank
3 Under Construction Power Backup
4 Under Construction Lobby
5 Under Construction Stairs
6 Not Started Lift
7 Not Started Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download