WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

ARUN NIBAS

Project Status as on Quarter ending 31-03-2024
Updated as on 16-04-2024

Booking Status

  • Residential Apartments Booked
    16

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    5

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Completed Without CC
1 2 Completed Without CC
1 3 Completed Without CC
1 4 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 internal wall
2 bathroom
3 toilet
4 staircases
5 lift
6 Electrical room

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC roof of building
2 Completed Without CC security room
3 Completed Without CC parking slot

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download