AMBEY GATEWAY

Project Status as on Quarter ending 31-03-2024
Updated as on 06-04-2024

Booking Status

  • Residential Apartments Booked
    186

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    70

  • Covered Car Parking Booked
    50

  • Mechanical Parking Booked
    52

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Completed Without CC
1 2 Completed Without CC
1 3 Completed Without CC
1 4 Completed Without CC
1 5 Completed Without CC
1 6 Completed Without CC
1 7 Completed Without CC
1 8 Completed Without CC
1 9 Under Construction
2 1 Completed Without CC
2 2 Completed Without CC
2 3 Completed Without CC
2 4 Completed Without CC
2 5 Completed Without CC
2 6 Completed Without CC
2 7 Completed Without CC
2 8 Completed Without CC
2 9 Completed Without CC
3 1 Completed Without CC
3 2 Completed Without CC
3 3 Completed Without CC
3 5 Completed Without CC
3 6 Completed Without CC
3 7 Completed Without CC
3 8 Completed Without CC
3 9 Completed Without CC
4 1 Completed Without CC
4 2 Completed Without CC
3 4 Completed Without CC
4 3 Completed Without CC
4 4 Completed Without CC
4 5 Completed Without CC
4 6 Completed Without CC
4 7 Completed Without CC
4 8 Completed Without CC
4 9 Completed Without CC
5 1 Completed Without CC
5 2 Completed Without CC
5 3 Completed Without CC
5 4 Completed Without CC
5 5 Completed Without CC
5 6 Completed Without CC
5 7 Completed Without CC
5 8 Completed Without CC
5 9 Completed Without CC
6 1 Completed Without CC
6 2 Completed Without CC
6 3 Completed Without CC
6 4 Completed Without CC
6 5 Completed Without CC
6 6 Completed Without CC
6 7 Completed Without CC
6 8 Completed Without CC
6 9 Completed Without CC
7 1 Under Construction
7 2 Not Started
7 3 Not Started
7 4 Not Started
CLUB HOUSE 1 Completed Without CC
CLUB HOUSE 2 Completed Without CC
CLUB HOUSE 3 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 TOWER -1 ELECTRICAL
2 TOWER -1 DOOR & WINDOW
3 TOWER -2 ELECTRICAL
4 TOWER -2 DOOR & WINDOW
5 TOWER -3 ELECTRICAL
6 TOWER -3 DOOR & WINDOW
7 TOWER -4 PHE
8 TOWER -4 ELECTRICAL
9 TOWER -4 DOOR & WINDOW
10 TOWER -5 PHE
11 TOWER -5 ELECTRICAL
12 TOWER -5 DOOR & WINDOW
13 TOWER -6 PHE
14 TOWER -6 ELECTRICAL
15 TOWER -6 FIRE PROTECTION & DETECTION
16 TOWER -6 DOOR & WINDOW
17 TOWER -6 FLOORING
18 TOWER -6 POP/PAINTING
19 CLUB HOUSE - ELECTRICAL

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Height clearance from Airport Authority of India (if any) 20-06-2023 30-09-2023 27-09-2023