WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Pasari Group Chitrakatha

Project Status as on Quarter ending 31-03-2024
Updated as on 01-04-2024

Booking Status

  • Residential Apartments Booked
    19

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    7

  • Mechanical Parking Booked
    12

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block A 1 Under Construction
Block A 2 Not Started
Block A 3 Not Started
Block A 4 Not Started
Block A 5 Not Started
Block A 6 Not Started
Block A 7 Not Started
Block B 1 Not Started
Block B 2 Not Started
Block B 3 Not Started
Block B 4 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Facility
2 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Lift
2 Roof
3 Septic Tank
4 Power Backup
5 Floor
6 Stairs

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download