WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Bhagwani Kunj

Project Status as on Quarter ending 31-03-2024
Updated as on 06-04-2024

Booking Status

  • Residential Apartments Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 - Residential 1 Under Construction
Block 1 - Residential 2 Not Started
Block 1 - Residential 3 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 emergency evacuation
2 fire facilities
3 water facilities

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 lobby
2 stairs
3 lift
4 roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download