Project Status as on Quarter ending 31-03-2024
Updated as on 04-04-2024

Booking Status

  • Residential Apartments Booked
    83

  • Basement Parking Booked
    23

  • Covered Car Parking Booked
    84

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block A - Wing 1- 1st to 10th Floor 1 Under Construction
Block A - Wing 1- 1st to 10th Floor 2 Under Construction
Block A - Wing 1- 1st to 10th Floor 3 Under Construction
Block A - Wing 1- 1st to 10th Floor 4 Under Construction
Block A - Wing 1- 1st to 10th Floor 5 Under Construction
Block A - Wing 1- 1st to 10th Floor 6 Under Construction
Block A - Wing 1- 1st to 10th Floor 7 Under Construction
Block A - Wing 1- 1st to 10th Floor 8 Under Construction
Block A - Wing 1- 1st to 10th Floor 9 Under Construction
Block A - Wing 1- 1st to 10th Floor 10 Under Construction
Block A - Wing 2- 1st to 10th Floor 1 Under Construction
Block A - Wing 2- 1st to 10th Floor 2 Under Construction
Block A - Wing 2- 1st to 10th Floor 3 Under Construction
Block A - Wing 2- 1st to 10th Floor 4 Under Construction
Block A - Wing 2- 1st to 10th Floor 5 Under Construction
Block A - Wing 2- 1st to 10th Floor 6 Under Construction
Block A - Wing 2- 1st to 10th Floor 7 Under Construction
Block A - Wing 2- 1st to 10th Floor 8 Under Construction
Block A - Wing 2- 1st to 10th Floor 9 Under Construction
Block A - Wing 2- 1st to 10th Floor 10 Under Construction
Block A - Wing 3 - 1st to 10th Floor 1 Under Construction
Block A - Wing 3 - 1st to 10th Floor 2 Under Construction
Block A - Wing 3 - 1st to 10th Floor 3 Under Construction
Block A - Wing 3 - 1st to 10th Floor 4 Under Construction
Block A - Wing 3 - 1st to 10th Floor 5 Under Construction
Block A - Wing 3 - 1st to 10th Floor 6 Under Construction
Block A - Wing 3 - 1st to 10th Floor 7 Under Construction
Block A - Wing 3 - 1st to 10th Floor 8 Under Construction
Block A - Wing 3 - 1st to 10th Floor 9 Under Construction
Block A - Wing 3 - 1st to 10th Floor 10 Under Construction
Block B - Wing 4 - 1st to 8th Floor 1 Under Construction
Block B - Wing 4 - 1st to 8th Floor 2 Under Construction
Block B - Wing 4 - 1st to 8th Floor 3 Under Construction
Block B - Wing 4 - 1st to 8th Floor 4 Under Construction
Block B - Wing 4 - 1st to 8th Floor 5 Under Construction
Block B - Wing 4 - 1st to 8th Floor 6 Under Construction
Block B - Wing 4 - 1st to 8th Floor 7 Under Construction
Block B - Wing 4 - 1st to 8th Floor 8 Under Construction
Block B - Wing 5 - 1st to 8th Floor 1 Under Construction
Block B - Wing 5 - 1st to 8th Floor 2 Under Construction
Block B - Wing 5 - 1st to 8th Floor 3 Under Construction
Block B - Wing 5 - 1st to 8th Floor 4 Under Construction
Block B - Wing 5 - 1st to 8th Floor 5 Under Construction
Block B - Wing 5 - 1st to 8th Floor 6 Under Construction
Block B - Wing 5 - 1st to 8th Floor 7 Under Construction
Block B - Wing 5 - 1st to 8th Floor 8 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Emergency Evacuation
2 WATER FACILITIES
3 FIRE AND FIGHTING

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction LOBBY
2 Under Construction STAIRS
3 Not Started LIFT
4 Not Started ROOF
5 Under Construction SEPTIC TANK
6 Under Construction Power Backup

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download