WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

DEVALOKE SONARCITY PHASE III

Project Status as on Quarter ending 31-03-2024
Updated as on 04-04-2024

Booking Status

  • Residential Apartments Booked
    7

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    6

  • Mechanical Parking Booked
    1

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 16 - 1st to 12th Floor - Residential 1 Under Construction
Block 16 - 1st to 12th Floor - Residential 2 Under Construction
Block 16 - 1st to 12th Floor - Residential 3 Not Started
Block 16 - 1st to 12th Floor - Residential 4 Not Started
Block 16 - 1st to 12th Floor - Residential 5 Not Started
Block 16 - 1st to 12th Floor - Residential 6 Not Started
Block 16 - 1st to 12th Floor - Residential 7 Not Started
Block 16 - 1st to 12th Floor - Residential 8 Not Started
Block 16 - 1st to 12th Floor - Residential 9 Not Started
Block 16 - 1st to 12th Floor - Residential 10 Not Started
Block 16 - 1st to 12th Floor - Residential 11 Not Started
Block 16 - 1st to 12th Floor - Residential 12 Not Started
Block 17 - 1st to 12th Floor - Residential 1 Under Construction
Block 17 - 1st to 12th Floor - Residential 2 Not Started
Block 17 - 1st to 12th Floor - Residential 3 Not Started
Block 17 - 1st to 12th Floor - Residential 4 Not Started
Block 17 - 1st to 12th Floor - Residential 5 Not Started
Block 17 - 1st to 12th Floor - Residential 6 Not Started
Block 17 - 1st to 12th Floor - Residential 7 Not Started
Block 17 - 1st to 12th Floor - Residential 8 Not Started
Block 17 - 1st to 12th Floor - Residential 9 Not Started
Block 17 - 1st to 12th Floor - Residential 10 Not Started
Block 17 - 1st to 12th Floor - Residential 11 Not Started
Block 17 - 1st to 12th Floor - Residential 12 Not Started
Block 18 - 1st to 12th Floor - Residential 1 Under Construction
Block 18 - 1st to 12th Floor - Residential 2 Under Construction
Block 18 - 1st to 12th Floor - Residential 3 Under Construction
Block 18 - 1st to 12th Floor - Residential 4 Under Construction
Block 18 - 1st to 12th Floor - Residential 5 Under Construction
Block 18 - 1st to 12th Floor - Residential 6 Under Construction
Block 18 - 1st to 12th Floor - Residential 7 Under Construction
Block 18 - 1st to 12th Floor - Residential 8 Under Construction
Block 18 - 1st to 12th Floor - Residential 9 Under Construction
Block 18 - 1st to 12th Floor - Residential 10 Under Construction
Block 18 - 1st to 12th Floor - Residential 11 Under Construction
Block 18 - 1st to 12th Floor - Residential 12 Under Construction
Block 19 - 1st to 12th Floor - Residential 1 Under Construction
Block 19 - 1st to 12th Floor - Residential 2 Under Construction
Block 19 - 1st to 12th Floor - Residential 3 Under Construction
Block 19 - 1st to 12th Floor - Residential 4 Under Construction
Block 19 - 1st to 12th Floor - Residential 5 Under Construction
Block 19 - 1st to 12th Floor - Residential 6 Under Construction
Block 19 - 1st to 12th Floor - Residential 7 Under Construction
Block 19 - 1st to 12th Floor - Residential 8 Under Construction
Block 19 - 1st to 12th Floor - Residential 9 Under Construction
Block 19 - 1st to 12th Floor - Residential 10 Under Construction
Block 19 - 1st to 12th Floor - Residential 11 Under Construction
Block 19 - 1st to 12th Floor - Residential 12 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Facility
2 Fire Facility
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Lobby
2 Staircase
3 Lift
4 Roof
5 Under Construction Fire Pump
6 Under Construction Front Gate and Back Gate
7 Under Construction TOILET PLUMBING
8 Under Construction ELECTRICAL WORK

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download