Project Status as on Quarter ending 31-03-2024
Updated as on 06-04-2024

Booking Status

  • Residential Apartments Booked
    66

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    57

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower 1- Block-1 1 Under Construction
Tower 1- Block-1 2 Under Construction
Tower 1- Block-1 3 Under Construction
Tower 1- Block-1 4 Under Construction
Tower 1- Block -2 1 Under Construction
Tower 1- Block -2 2 Under Construction
Tower 1- Block -2 3 Under Construction
Tower 1- Block -2 4 Under Construction
Tower 1- Block-3 1 Under Construction
Tower 1- Block-3 2 Under Construction
Tower 1- Block-3 3 Under Construction
Tower 1- Block-3 4 Under Construction
Tower 1- Block 4 1 Under Construction
Tower 1- Block 4 2 Under Construction
Tower 1- Block 4 3 Under Construction
Tower 1- Block 4 4 Under Construction
Tower 1- Block 5 1 Under Construction
Tower 1- Block 5 2 Under Construction
Tower 1- Block 5 3 Under Construction
Tower 1- Block 5 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Facility
2 Fire Facility
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Lobby
2 Stairs
3 Lift
4 Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download