WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Panchmukhi Pearl

Project Status as on Quarter ending 31-03-2024
Updated as on 04-04-2024

Booking Status

  • Residential Apartments Booked
    16

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    9

  • Mechanical Parking Booked
    4

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK-C (G+4) 1 Under Construction
BLOCK-C (G+4) 2 Under Construction
BLOCK-C (G+4) 3 Not Started
BLOCK-C (G+4) 4 Not Started
BLOCK-D(G+12) 1 Under Construction
BLOCK-D(G+12) 2 Under Construction
BLOCK-D(G+12) 3 Under Construction
BLOCK-D(G+12) 4 Under Construction
BLOCK-D(G+12) 5 Under Construction
BLOCK-D(G+12) 6 Under Construction
BLOCK-D(G+12) 7 Under Construction
BLOCK-D(G+12) 8 Under Construction
BLOCK-D(G+12) 9 Under Construction
BLOCK-D(G+12) 10 Under Construction
BLOCK-D(G+12) 11 Under Construction
BLOCK-D(G+12) 12 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Emergency Evacuation Services
2 Fire Fighting Facilty
3 Use of Renewable Energy
4 Drinking Water Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Stairs
2 Under Construction Lift
3 Under Construction Roof
4 Under Construction Lobby
5 Under Construction Septic tank
6 Under Construction Power Backup

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download