WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

SIDDHA SKY PHASE II (BLU)

Project Status as on Quarter ending 31-03-2024
Updated as on 18-04-2024

Booking Status

  • Residential Apartments Booked
    17

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    19

  • Mechanical Parking Booked
    14

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block - C 1 Not Started
Block - C 2 Not Started
Block - C 3 Not Started
Block - C 4 Not Started
Block - C 5 Not Started
Block - C 6 Not Started
Block - C 7 Not Started
Block - C 8 Not Started
Block - C 9 Not Started
Block - C 10 Not Started
Block - C 11 Not Started
Block - C 12 Not Started
Block - C 13 Not Started
Block - C 14 Not Started
Block - C 15 Not Started
Block - C 16 Not Started
Block - C 17 Not Started
Block - C 18 Not Started
Block - C 19 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities
2 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Club
2 Not Started Power Backup
3 Not Started Stairs
4 Not Started Lift
5 Not Started Lobby
6 Not Started Roof
7 Not Started Septic Tank
8 Not Started Overhead Tank
9 Not Started Water Reservoir
10 Under Construction Swimming Pool
11 Under Construction MLCP

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download