Project Status as on Quarter ending 31-03-2024
Updated as on 06-04-2024

Booking Status

  • Residential Apartments Booked
    4

  • Commercial Unit Booked
    9

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    2

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
LOWER GROUND FLOOR COMMERCIAL 1 Completed With CC
ELEVATED GROUND FLOOR COMMERCIAL 1 Completed With CC
BLOCK 1 1 Completed With CC
BLOCK 1 2 Completed With CC
BLOCK 1 3 Completed With CC
BLOCK 1 4 Completed With CC
BLOCK 1 5 Completed With CC
BLOCK 1 6 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Common Area, Parking, Roof & Overall Building

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Fire NOC 01-04-2023 10-06-2023 18-06-2023 No Modification, Amendment or Revision
Other 15-10-2023 31-12-2023 01-02-2024